2020 Da-Tan Power Plant of Taiwan Power Co. No. 5 / MHI 501G Gas Turbine, #5-1 & #5-2 HRSG Retrofit, installed SCR
2020-04-06 11:36
?
(2020 Da-Tan Power Plant of Taiwan Power Co. No. 5 / MHI 501G Gas Turbine, #5-1 & #5-2 HRSG Retrofit, installed SCR )Through totally 15 days of efficiency examination by Load 100%, 90%, 80% , 70% & AGC for each 3 days) withExcellent results : DeNOx: >84% ( Outlet<4ppm ) Ammonia slip <1 ppm SCR D.P.: <0.5 kpa
?


?


?

?

?

?

?